Clevedon Water and Wastewater Network

Client

Brian Perry Civil

Location

South Auckland

Completed

Current (still constructing)

Challenge

Network improvements through the Clevedon Area (to and from the Ardmore pump station) are necessary for network growth and resilience. Unfortunately the road network in this area is a series of narrower high speed roads giving little room to accommodate construction concurrent with normal traffic flow.

Solution

Barrier system selection on this project was important - aiming to balance manoeuvrability with rigidity - which resulted in a new way of determining operating speed for carriageways and a risk-based approach to site design which has been a blueprint for other similar road environments since.

Results

The result was a highly flexible working space solutiuon that allowed for high productivity rates but also ensured protection of road users and road workers alike.

Team

Kava Aloua
Jolina Mendoza

Equipment used

Coming soon

Tags

<   Back to Projects